29INR0292 · BESS · Borden County
Enfinity Post Oak Storage SLF
Enfinity Post Oak Storage SLF is a 0 MW battery storage project in Borden County, Texas, connecting at 345kV MULESHOE (#59922). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/18/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 29INR0292
- Capacity
- 0 MW
- Fuel
- BESS (BA)
- Substation
- 345kV MULESHOE (#59922)
- County
- Borden County
- Interconnecting entity
- EG White Oak LLC
- Projected COD
- 12/18/2029
- Entered queue
- 03/27/2026
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/27/2026Entered the queue with 0 MW, projected COD 12/18/2029
- 03/27/2026Screening → FIS Requested
Other projects at this substation
| Lyra Storage | BESS | 500 MW | IA Signed |
| Lyra Solar | Solar | 500 MW | IA Signed |
| Enfinity Post Oak Solar SLF | Solar | 500 MW | FIS Requested |