LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0636 · BESS · Borden County

Lyra Storage

Lyra Storage is a 500 MW battery storage project in Borden County, Texas, connecting at 345kV MULESHOE (#59922). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 11/12/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0636
Capacity
500 MW
Fuel
BESS (BA)
Interconnecting entity
JUNO BESS I
Projected COD
11/12/2026
Entered queue
05/12/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/13/2025
    FIS Requested → IA Signed
  • 05/12/2025
    Entered the queue with 500 MW, projected COD 11/12/2026
  • 05/12/2025
    Screening → FIS Requested

Other projects at this substation

Lyra SolarSolar500 MWIA Signed
Enfinity Post Oak Solar SLFSolar500 MWFIS Requested
Enfinity Post Oak Storage SLFBESS0 MWFIS Requested