29INR0226 · Solar · Baylor County

Velveteen Solar III

Velveteen Solar III is a 201 MW solar project in Baylor County, Texas, connecting at Tap into 6076 FOXTAIL- 6100 OKLAUNION. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/15/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0226
Capacity
201 MW
Fuel
Solar (PV)
Interconnecting entity
Velveteen Solar III, LLC
Projected COD
12/15/2029
Entered queue
12/09/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/09/2025
    Entered the queue with 201 MW, projected COD 12/15/2029
  • 12/09/2025
    Screening → FIS Requested

Other projects at this substation

Velveteen Solar ISolar502 MWFIS Requested
Velveteen Solar IISolar301 MWFIS Requested