LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
29INR0198 · Solar · Baylor County

Velveteen Solar I

Velveteen Solar I is a 502 MW solar project in Baylor County, Texas, connecting at Tap into 6076 FOXTAIL- 6100 OKLAUNION. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/15/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0198
Capacity
502 MW
Fuel
Solar (PV)
Interconnecting entity
Velveteen Solar, LLC
Projected COD
10/15/2029
Entered queue
12/19/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/19/2025
    Entered the queue with 502 MW, projected COD 10/15/2029
  • 12/19/2025
    Screening → FIS Requested

Other projects at this substation

Velveteen Solar IISolar301 MWFIS Requested
Velveteen Solar IIISolar201 MWFIS Requested