LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0105 · Gas · Ward County

Vast Sands Power I (TEF -Due Diligence)

Vast Sands Power I (TEF -Due Diligence) is a 440 MW natural gas project in Ward County, Texas, connecting at Tap 345kV 11010 Wolf Switch - 11188 Quarry Field Switch Ckt 2. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 05/01/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0105
Capacity
440 MW
Fuel
Gas (GT)
Interconnecting entity
Permian Power I LLC
Projected COD
05/01/2028
Entered queue
07/05/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/16/2026
    FIS Requested → FIS Approved
  • 10/31/2025
    FIS Approved → IA Signed
  • 07/05/2024
    Entered the queue with 440 MW, projected COD 05/01/2028
  • 07/05/2024
    Screening → FIS Requested

Other projects at this substation