ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0087 · Gas · Lamar County

North Royal Thermal (TEF- Due Diligence)

North Royal Thermal (TEF- Due Diligence) is a 479 MW natural gas project in Lamar County, Texas, connecting at Tap 345kV 1695 MOSES_5 - 11699 WOODARD_5. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 08/01/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0087
Capacity
479 MW
Fuel
Gas (GT)
Interconnecting entity
Invenergy Energy Transition Development LLC
Projected COD
08/01/2030
Entered queue
06/13/2024
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/17/2024
    Screening → FIS Requested
  • 06/13/2024
    Entered the queue with 479 MW, projected COD 08/01/2030