LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0636 · Solar · Brazoria County

Myrtle Solar Repower

Myrtle Solar Repower is a 314 MW solar project in Brazoria County, Texas, connecting at 42110 Angleton 138kV. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 06/21/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0636
Capacity
314 MW
Fuel
Solar (PV)
Interconnecting entity
Myrtle Solar, LLC
Projected COD
06/21/2027
Entered queue
09/10/2026
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Entered the queue with 314 MW, projected COD 06/21/2027
  • 09/15/2026
    FIS Requested → FIS Approved
  • 09/10/2026
    Screening → FIS Requested

Other projects at this substation

Myrtle SolarSolar321 MWSync Approved