19INR0041 · Solar · Brazoria County

Myrtle Solar

Myrtle Solar is a 321 MW solar project in Brazoria County, Texas, connecting at 42110 Angleton 138kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 06/21/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
19INR0041
Capacity
321 MW
Fuel
Solar (PV)
Interconnecting entity
Myrtle Solar, LLC
Projected COD
06/21/2027
Entered queue
03/15/2017
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/20/2022
    Energization Approved → Sync Approved
  • 12/07/2022
    IA Signed → Energization Approved
  • 01/25/2022
    FIS Requested → FIS Approved
  • 11/13/2019
    FIS Approved → IA Signed
  • 05/09/2017
    Screening → FIS Requested
  • 03/15/2017
    Entered the queue with 321 MW, projected COD 06/21/2027