LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0493 · BESS · Ector County

Velociraptor BESS I

Velociraptor BESS I is a 246 MW battery storage project in Ector County, Texas, connecting at #10012 METEOR 5 Substation 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0493
Capacity
246 MW
Fuel
BESS (BA)
Interconnecting entity
Velociraptor BESS I, LLC
Projected COD
12/01/2029
Entered queue
05/07/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/07/2025
    Entered the queue with 246 MW, projected COD 12/01/2029
  • 05/07/2025
    Screening → FIS Requested

Other projects at this substation

Velociraptor Solar ISolar242 MWFIS Requested