22INR0218 · Solar · Ector County
Velociraptor Solar I
Velociraptor Solar I is a 242 MW solar project in Ector County, Texas, connecting at #10012 METEOR 5 Substation 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 22INR0218
- Capacity
- 242 MW
- Fuel
- Solar (PV)
- Substation
- #10012 METEOR 5 Substation 345kV
- County
- Ector County
- Interconnecting entity
- Velociraptor Solar I, LLC
- Projected COD
- 12/01/2029
- Entered queue
- 05/10/2019
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/10/2019Entered the queue with 242 MW, projected COD 12/01/2029
- 05/10/2019Screening → FIS Requested
Other projects at this substation
| Velociraptor BESS I | BESS | 246 MW | FIS Requested |