LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
22INR0218 · Solar · Ector County

Velociraptor Solar I

Velociraptor Solar I is a 242 MW solar project in Ector County, Texas, connecting at #10012 METEOR 5 Substation 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
22INR0218
Capacity
242 MW
Fuel
Solar (PV)
Interconnecting entity
Velociraptor Solar I, LLC
Projected COD
12/01/2029
Entered queue
05/10/2019
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/10/2019
    Entered the queue with 242 MW, projected COD 12/01/2029
  • 05/10/2019
    Screening → FIS Requested

Other projects at this substation

Velociraptor BESS IBESS246 MWFIS Requested