ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0466 · BESS · Calhoun County

Wolfram Storage

Wolfram Storage is a 207 MW battery storage project in Calhoun County, Texas, connecting at Dokmai 138kV Substation (bus #80090). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0466
Capacity
207 MW
Fuel
BESS (BA)
Interconnecting entity
Nova Clean Energy, LLC
Projected COD
12/01/2027
Entered queue
05/02/2025
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/02/2025
    Entered the queue with 207 MW, projected COD 12/01/2027
  • 05/02/2025
    Screening → FIS Requested

Other projects at this substation

HyFuels Green Lake SolarSolar347 MWFIS Requested