LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0019 · Solar · Calhoun County

HyFuels Green Lake Solar

HyFuels Green Lake Solar is a 347 MW solar project in Calhoun County, Texas, connecting at Dokmai 138kV Substation (bus #80090). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0019
Capacity
347 MW
Fuel
Solar (PV)
Interconnecting entity
HyFuels Green Lake Solar LLC
Projected COD
12/01/2027
Entered queue
09/27/2022
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/13/2023
    Screening → FIS Requested
  • 09/27/2022
    Entered the queue with 347 MW, projected COD 12/01/2027

Other projects at this substation

Wolfram StorageBESS207 MWFIS Requested