27INR0432 · BESS · Brown County
Coyote Ridge BESS
Coyote Ridge BESS is a 111 MW battery storage project in Brown County, Texas, connecting at 292 Holder 138 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/06/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0432
- Capacity
- 111 MW
- Fuel
- BESS (BA)
- Substation
- 292 Holder 138 kV
- County
- Brown County
- Interconnecting entity
- Grenergy USA
- Projected COD
- 10/06/2027
- Entered queue
- 01/15/2025
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/15/2025Entered the queue with 111 MW, projected COD 10/06/2027
- 01/15/2025Screening → FIS Requested
Other projects at this substation
No other projects at this substation.