27INR0409 · BESS · Lamar County

Baker Branch BESS

Baker Branch BESS is a 287 MW battery storage project in Lamar County, Texas, connecting at Pacific Switch (PACSW) 345 kV Bus 11683. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0409
Capacity
287 MW
Fuel
BESS (BA)
Interconnecting entity
Mockingbird Storage Center, LLC
Projected COD
12/31/2029
Entered queue
06/10/2025
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/10/2025
    Entered the queue with 287 MW, projected COD 12/31/2029
  • 06/10/2025
    Screening → FIS Requested