27INR0409 · BESS · Lamar County
Baker Branch BESS
Baker Branch BESS is a 287 MW battery storage project in Lamar County, Texas, connecting at Pacific Switch (PACSW) 345 kV Bus 11683. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0409
- Capacity
- 287 MW
- Fuel
- BESS (BA)
- Substation
- Pacific Switch (PACSW) 345 kV Bus 11683
- County
- Lamar County
- Interconnecting entity
- Mockingbird Storage Center, LLC
- Projected COD
- 12/31/2029
- Entered queue
- 06/10/2025
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/10/2025Entered the queue with 287 MW, projected COD 12/31/2029
- 06/10/2025Screening → FIS Requested
Other projects at this substation
No other projects at this substation.