Kingsmill Wind SLF is a 606 MW wind project in Carson County, Texas, connecting at 79005 Railhead 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/01/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0140
- Capacity
- 606 MW
- Fuel
- Wind (WT)
- Substation
- 79005 Railhead 345kV
- County
- Carson County
- Interconnecting entity
- Kingsmill Wind, LLC
- Projected COD
- 09/01/2029
- Entered queue
- 01/11/2024
- ERCOT zone
- PANHANDLE
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/18/2025FIS Requested → IA Signed
- 10/08/2024Screening → FIS Requested
- 01/11/2024Entered the queue with 606 MW, projected COD 09/01/2029