Carson County power projects

Carson County, Texas has 4 active power projects totalling 1,618 MW in ERCOT's interconnection queue as of the October 2026 report. Wind is the largest share at 606 MW (37%). The largest single project is Kingsmill Wind SLF (606 MW wind). 3 projects have signed an interconnection agreement or reached a later stage. 2 projects in the county are listed as withdrawn or cancelled.

Active projects
4
1.6 GW capacity
IA signed or later
3
75% of active projects
Withdrawn or cancelled
2
listed by ERCOT
Changes tracked
0
since Sep 2026

Changes in Carson County

No changes in the reports compared so far.

All projects

ProjectFuelMWSubstationStageCOD
Kingsmill Wind SLFWind60679005 Railhead 345kVIA Signed09/01/2029
Panhandle Flagship Solar 1Solar439345 kV Railhead Substation (RAILHEAD #79005)IA Signed06/30/2031
Panhandle Flagship StorageBESS372345 kV Railhead Substation (RAILHEAD #79005)IA Signed06/30/2031
Kota BatteryBESS20123900 Alibates 345kVFIS Requested10/31/2028
Corvette WindWind1,200Not listedWithdrawnn/a
Grandview 4 Phase A WindWind200Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Carson County?
ERCOT's October 2026 report lists 4 active projects in Carson County totalling 1,618 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.