Monahans Power Gas is a 18 MW natural gas project in Ward County, Texas, connecting at Tap #1107 Monahans Tap 2 to #11117 Pecos Trail 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/16/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0724
Capacity
18 MW
Fuel
Gas (IC)
Interconnecting entity
Liberty Power Innovations LLC
Projected COD
04/16/2030
Entered queue
09/22/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/26/2026
    Screening → FIS Requested
  • 09/22/2025
    Entered the queue with 18 MW, projected COD 04/16/2030