26INR0698 · Gas · Ward County

Staghorn Gas

Staghorn Gas is a 10 MW natural gas project in Ward County, Texas, connecting at STAGHORN. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 10/29/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0698
Capacity
10 MW
Fuel
Gas (IC)
Substation
STAGHORN
Interconnecting entity
RPC Merchant LLC
Projected COD
10/29/2026
Entered queue
05/30/2025
ERCOT zone
WEST
Size category
Small

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/18/2026
    Energization Approved → Sync Approved
  • 09/02/2026
    IA Signed → Energization Approved
  • 05/30/2025
    Entered the queue with 10 MW, projected COD 10/29/2026
  • 05/30/2025
    Screening → IA Signed

Other projects at this substation

No other projects at this substation.