26INR0640 · BESS · Cameron County
Amberjack2 BESS
Amberjack2 BESS is a 180 MW battery storage project in Cameron County, Texas, connecting at 79501 KINGFISHER 345KV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/03/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0640
- Capacity
- 180 MW
- Fuel
- BESS (BA)
- Substation
- 79501 KINGFISHER 345KV
- County
- Cameron County
- Interconnecting entity
- Hunt Energy Network, LLC
- Projected COD
- 04/03/2028
- Entered queue
- 01/06/2025
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/06/2025Entered the queue with 180 MW, projected COD 04/03/2028
- 01/06/2025Screening → FIS Requested
Other projects at this substation
No other projects at this substation.