26INR0430 · BESS · Mills County
Clapton Storage
Clapton Storage is a 209 MW battery storage project in Mills County, Texas, connecting at Tap 345 kV 3424 Buckhorn Switch - 1444 Brown Switch. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 08/09/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0430
- Capacity
- 209 MW
- Fuel
- BESS (BA)
- County
- Mills County
- Interconnecting entity
- Clapton BESS
- Projected COD
- 08/09/2028
- Entered queue
- 02/13/2024
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/13/2024Entered the queue with 209 MW, projected COD 08/09/2028
- 02/13/2024Screening → FIS Requested
Other projects at this substation