26INR0252 · BESS · Mclennan County
Neutron Storage
Neutron Storage is a 104 MW battery storage project in Mclennan County, Texas, connecting at Tap 345kV 13405 Trading House - 68090 Sam Switch. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 04/29/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0252
- Capacity
- 104 MW
- Fuel
- BESS (BA)
- County
- Mclennan County
- Interconnecting entity
- Elawan Neutron Storage, LLC
- Projected COD
- 04/29/2028
- Entered queue
- 08/21/2023
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/05/2025FIS Approved → IA Signed
- 05/16/2025FIS Requested → FIS Approved
- 08/21/2023Entered the queue with 104 MW, projected COD 04/29/2028
- 08/21/2023Screening → FIS Requested
Other projects at this substation
No other projects at this substation.