26INR0243 · BESS · Waller County
Caladium BESS
Caladium BESS is a 201 MW battery storage project in Waller County, Texas, connecting at 57664 Sunnyside 69kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 11/30/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0243
- Capacity
- 201 MW
- Fuel
- BESS (BA)
- Substation
- 57664 Sunnyside 69kV
- County
- Waller County
- Interconnecting entity
- Caladium Storage, LLC
- Projected COD
- 11/30/2027
- Entered queue
- 10/29/2024
- ERCOT zone
- HOUSTON
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/29/2024Entered the queue with 201 MW, projected COD 11/30/2027
- 10/29/2024Screening → FIS Requested