Counties / Texas
Waller County power projects
Waller County, Texas has 5 active power projects totalling 924 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 566 MW (61%). The largest single project is Twinwood Solar 1 (358 MW solar). 3 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
5
0.9 GW capacity
IA signed or later
3
60% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
0
since Sep 2026
Changes in Waller County
No changes in the reports compared so far.
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Twinwood Solar 1 | Solar | 358 | Tap 138kV 44750 FULSHR_S25_8 - 44860 TWINWD_S25_8 | IA Signed | 02/01/2029 |
| Caladium BESS | BESS | 201 | 57664 Sunnyside 69kV | FIS Requested | 11/30/2027 |
| Augie BESS | BESS | 201 | 46560 Waller 138kV | FIS Approved | 12/17/2027 |
| Maderagemela BESS1 | BESS | 154 | Tap 138kV 44750 FULSHR_S25_8 to 44860 TWINWD_S25_8 | IA Signed | 02/01/2029 |
| Seaway BESS | BESS | 10 | Seaway | IA Signed | 02/22/2027 |
For residents and landowners
- What power projects are planned in Waller County?
- ERCOT's October 2026 report lists 5 active projects in Waller County totalling 924 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.