26INR0162 · BESS · Nacogdoches County
Timberline Storage
Timberline Storage is a 100 MW battery storage project in Nacogdoches County, Texas, connecting at Tap 345 kV 3119 Nacogdoches SE - 3116 Mt Enterprise. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/05/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0162
- Capacity
- 100 MW
- Fuel
- BESS (BA)
- County
- Nacogdoches County
- Interconnecting entity
- Timberline Renewables, LLC
- Projected COD
- 10/05/2029
- Entered queue
- 08/04/2023
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/04/2023Entered the queue with 100 MW, projected COD 10/05/2029
- 08/04/2023Screening → FIS Requested
Other projects at this substation
| Timberline Solar | Solar | 201 MW | FIS Requested |