26INR0111 · Gas · Mclennan County
Graphic Packaging Gas
Graphic Packaging Gas is a 43 MW natural gas project in Mclennan County, Texas, connecting at Tap 138kV 3446 Peppervine Switch - 3544 Castleman Substation. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 02/15/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0111
- Capacity
- 43 MW
- Fuel
- Gas (GT)
- County
- Mclennan County
- Interconnecting entity
- Graphic Packaging International
- Projected COD
- 02/15/2027
- Entered queue
- 01/05/2024
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/30/2026FIS Approved → IA Signed
- 12/03/2024FIS Requested → FIS Approved
- 01/05/2024Entered the queue with 43 MW, projected COD 02/15/2027
- 01/05/2024Screening → FIS Requested