26INR0008 · Solar · Cameron County
Puerto Del Sol 1
Puerto Del Sol 1 is a 214 MW solar project in Cameron County, Texas, connecting at Tap 345kV 79500 Palmito - 79501 King Fisher Ckt 1. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0008
- Capacity
- 214 MW
- Fuel
- Solar (PV)
- County
- Cameron County
- Interconnecting entity
- PUERTO DEL SOL, LLC
- Projected COD
- 12/31/2026
- Entered queue
- 05/16/2022
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/13/2023Screening → FIS Requested
- 05/16/2022Entered the queue with 214 MW, projected COD 12/31/2026
Other projects at this substation
| Puerto Del Sol 2 | Solar | 214 MW | FIS Requested |