25INR0606 · Solar · Ward County
Proteus Thornton Ranch Solar SLF
Proteus Thornton Ranch Solar SLF is a 180 MW solar project in Ward County, Texas, connecting at 37990 TNSTAGHORN1 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 11/20/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0606
- Capacity
- 180 MW
- Fuel
- Solar (PV)
- Substation
- 37990 TNSTAGHORN1 138kV
- County
- Ward County
- Interconnecting entity
- Thornton Ranch Solar, LLC
- Projected COD
- 11/20/2028
- Entered queue
- 02/12/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/12/2024Entered the queue with 180 MW, projected COD 11/20/2028
- 02/12/2024Screening → FIS Requested
Other projects at this substation
| Proteus Thornton Ranch Storage SLF | BESS | 0 MW | FIS Requested |