25INR0579 · BESS · Mclennan County

Albatross BESS 2

Albatross BESS 2 is a 160 MW battery storage project in Mclennan County, Texas, connecting at Tap 138kV 165 Windsor Switch - 161 McGregor. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/30/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0579
Capacity
160 MW
Fuel
BESS (BA)
Interconnecting entity
Albatross Solar, LLC
Projected COD
12/30/2028
Entered queue
01/03/2024
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/02/2026
    FIS Approved → IA Signed
  • 10/30/2025
    FIS Requested → FIS Approved
  • 01/03/2024
    Entered the queue with 160 MW, projected COD 12/30/2028
  • 01/03/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.