25INR0552 · BESS · Cameron County
HarryoungBESS
HarryoungBESS is a 190 MW battery storage project in Cameron County, Texas, connecting at 8319 Rio Hondo sub 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/15/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0552
- Capacity
- 190 MW
- Fuel
- BESS (BA)
- Substation
- 8319 Rio Hondo sub 138kV
- County
- Cameron County
- Interconnecting entity
- Gransolar Texas Four LLC
- Projected COD
- 05/15/2028
- Entered queue
- 09/19/2023
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/19/2023Entered the queue with 190 MW, projected COD 05/15/2028
- 09/19/2023Screening → FIS Requested
Other projects at this substation
No other projects at this substation.