25INR0505 · Solar · Lamar County

Mud Cat Solar SLF

Mud Cat Solar SLF is a 100 MW solar project in Lamar County, Texas, connecting at Tap 138KV 11768 Hawk Hollow – 1768 Deport. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/18/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0505
Capacity
100 MW
Fuel
Solar (PV)
Interconnecting entity
Mud Cat Solar, LLC
Projected COD
09/18/2028
Entered queue
10/20/2023
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/14/2024
    Screening → FIS Requested
  • 10/20/2023
    Entered the queue with 100 MW, projected COD 09/18/2028