25INR0451 · BESS · Upton County

Tres Rios Ranch BESS

Tres Rios Ranch BESS is a 290 MW battery storage project in Upton County, Texas, connecting at 76008 Twelvemile 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/31/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0451
Capacity
290 MW
Fuel
BESS (BA)
Interconnecting entity
LectricWind LLC
Projected COD
12/31/2027
Entered queue
05/23/2023
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/30/2025
    FIS Requested → IA Signed
  • 05/23/2023
    Entered the queue with 290 MW, projected COD 12/31/2027
  • 05/23/2023
    Screening → FIS Requested

Other projects at this substation

Tres Rios Ranch SolarSolar508 MWIA Signed