ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0404 · Solar · Upton County

Tres Rios Ranch Solar

Tres Rios Ranch Solar is a 508 MW solar project in Upton County, Texas, connecting at 76008 Twelvemile 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/31/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0404
Capacity
508 MW
Fuel
Solar (PV)
Interconnecting entity
LectricWind LLC
Projected COD
12/31/2027
Entered queue
08/05/2022
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/30/2025
    FIS Requested → IA Signed
  • 04/26/2023
    Screening → FIS Requested
  • 08/05/2022
    Entered the queue with 508 MW, projected COD 12/31/2027

Other projects at this substation

Tres Rios Ranch BESSBESS290 MWIA Signed