25INR0334 · BESS · Lamar County

Star Dairy Storage

Star Dairy Storage is a 205 MW battery storage project in Lamar County, Texas, connecting at Tap 345kV 1692 PARIS_SW1_5 -- 11699 WOODARD_5. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/12/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0334
Capacity
205 MW
Fuel
BESS (BA)
Interconnecting entity
Star Dairy Storage
Projected COD
07/12/2027
Entered queue
04/11/2023
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/16/2026
    FIS Requested → FIS Approved
  • 12/09/2024
    FIS Approved → IA Signed
  • 04/11/2023
    Entered the queue with 205 MW, projected COD 07/12/2027
  • 04/11/2023
    Screening → FIS Requested

Other projects at this substation