25INR0334 · BESS · Lamar County
Star Dairy Storage
Star Dairy Storage is a 205 MW battery storage project in Lamar County, Texas, connecting at Tap 345kV 1692 PARIS_SW1_5 -- 11699 WOODARD_5. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/12/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0334
- Capacity
- 205 MW
- Fuel
- BESS (BA)
- County
- Lamar County
- Interconnecting entity
- Star Dairy Storage
- Projected COD
- 07/12/2027
- Entered queue
- 04/11/2023
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/16/2026FIS Requested → FIS Approved
- 12/09/2024FIS Approved → IA Signed
- 04/11/2023Entered the queue with 205 MW, projected COD 07/12/2027
- 04/11/2023Screening → FIS Requested
Other projects at this substation
| Star Dairy Solar | Solar | 116 MW | IA Signed |