25INR0270 · Solar · Cameron County
Harryoung Solar
Harryoung Solar is a 190 MW solar project in Cameron County, Texas, connecting at Tap 8319 Rio Hondo - SOUTH SANTA ROSA: 8359, 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/15/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0270
- Capacity
- 190 MW
- Fuel
- Solar (PV)
- County
- Cameron County
- Interconnecting entity
- Gransolar Texas Four LLC
- Projected COD
- 05/15/2028
- Entered queue
- 11/23/2022
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/14/2023Screening → FIS Requested
- 11/23/2022Entered the queue with 190 MW, projected COD 05/15/2028
Other projects at this substation
No other projects at this substation.