ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0177 · Wind · Cottle County

Triangle Ranch Alpha

Triangle Ranch Alpha is a 302 MW wind project in Cottle County, Texas, connecting at Edith Clark 345 kV (#60500). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0177
Capacity
302 MW
Fuel
Wind (WT)
Interconnecting entity
Triangle Ranch Wind
Projected COD
07/01/2029
Entered queue
09/15/2022
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/15/2022
    Entered the queue with 302 MW, projected COD 07/01/2029
  • 09/15/2022
    Screening → FIS Requested

Other projects at this substation

Triangle Ranch BravoWind200 MWFIS Requested