Cottle County power projects

Cottle County, Texas has 4 active power projects totalling 906 MW in ERCOT's interconnection queue as of the October 2026 report. Wind is the largest share at 502 MW (55%). The largest single project is Triangle Ranch Alpha (302 MW wind). 0 projects have signed an interconnection agreement or reached a later stage. 4 projects in the county are listed as withdrawn or cancelled.

Active projects
4
0.9 GW capacity
IA signed or later
0
0% of active projects
Withdrawn or cancelled
4
listed by ERCOT
Changes tracked
0
since Sep 2026

Changes in Cottle County

No changes in the reports compared so far.

All projects

ProjectFuelMWSubstationStageCOD
Triangle Ranch AlphaWind302Edith Clark 345 kV (#60500)FIS Requested07/01/2029
Soluce Cotton SolarSolar203Tap 345kV 59904 COTTONWOOD - 60500 EDITH CLARKEScreening08/13/2029
Soluce Cotton StorageBESS202Tap 345kV 59904 COTTONWOOD - 60500 EDITH CLARKEScreening08/13/2029
Triangle Ranch BravoWind200Edith Clark 345 kV (#60500)FIS Requested07/01/2028
Triangle Ranch CharlieWind200Not listedWithdrawnn/a
Triangle Ranch DeltaWind102Not listedWithdrawnn/a
Triangle Ranch EchoWind100Not listedWithdrawnn/a
Triangle Ranch FoxWind100Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Cottle County?
ERCOT's October 2026 report lists 4 active projects in Cottle County totalling 906 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.