24INR0572 · BESS · Cameron County
Megacharge BESS
Megacharge BESS is a 110 MW battery storage project in Cameron County, Texas, connecting at 8320 WEST HARLINGEN 69kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0572
- Capacity
- 110 MW
- Fuel
- BESS (BA)
- Substation
- 8320 WEST HARLINGEN 69kV
- County
- Cameron County
- Interconnecting entity
- SMT Harlingen III LLC
- Projected COD
- 07/01/2028
- Entered queue
- 06/26/2023
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/26/2023Entered the queue with 110 MW, projected COD 07/01/2028
- 06/26/2023Screening → FIS Requested