24INR0544 · BESS · Brown County
Wetzel BESS
Wetzel BESS is a 186 MW battery storage project in Brown County, Texas, connecting at Tap 138kV 1654 Zephyr – 1655 Brownwood Switch. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/09/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0544
- Capacity
- 186 MW
- Fuel
- BESS (BA)
- County
- Brown County
- Interconnecting entity
- Brown ESS, LLC
- Projected COD
- 09/09/2028
- Entered queue
- 03/15/2023
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/15/2023Entered the queue with 186 MW, projected COD 09/09/2028
- 03/15/2023Screening → FIS Requested