24INR0455 · BESS · Pecos County
Longfellow BESS II
COD delayed 1×
Longfellow BESS II is a 106 MW battery storage project in Pecos County, Texas, connecting at 38432 TNCENTRY2_1 138 KV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 03/30/2028. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0455
- Capacity
- 106 MW
- Fuel
- BESS (BA)
- Substation
- 38432 TNCENTRY2_1 138 KV
- County
- Pecos County
- Interconnecting entity
- CENTURY GAS PROCESSING, LLC
- Projected COD
- 03/30/2028
- Entered queue
- 11/07/2022
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 11/30/2026 → 03/30/2028 (+16 months)
- 12/17/2025FIS Requested → FIS Approved
- 04/15/2025FIS Approved → IA Signed
- 04/12/2023Screening → FIS Requested
- 11/07/2022Entered the queue with 106 MW, projected COD 11/30/2026
Other projects at this substation
| Longfellow Solar II | Solar | 207 MW | IA Signed |