ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0454 · Solar · Pecos County

Longfellow Solar II

Longfellow Solar II is a 207 MW solar project in Pecos County, Texas, connecting at 38432 TNCENTRY2_1 138 KV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/31/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0454
Capacity
207 MW
Fuel
Solar (PV)
Interconnecting entity
CENTURY GAS PROCESSING, LLC
Projected COD
12/31/2028
Entered queue
11/07/2022
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/15/2025
    FIS Requested → IA Signed
  • 04/13/2023
    Screening → FIS Requested
  • 11/07/2022
    Entered the queue with 207 MW, projected COD 12/31/2028

Other projects at this substation

Longfellow BESS IIBESS106 MWIA Signed