ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0339 · Solar · Kaufman County

Mystic Springs Renewable Energy Solar SLF

Mystic Springs Renewable Energy Solar SLF is a 259 MW solar project in Kaufman County, Texas, connecting at Tap 345 kV Royse Switch (2478) – Poetry Switch (2485). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 03/31/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0339
Capacity
259 MW
Fuel
Solar (PV)
Interconnecting entity
Mystic Spring Renewable Energy LLC
Projected COD
03/31/2028
Entered queue
05/10/2022
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/30/2025
    FIS Approved → IA Signed
  • 04/17/2025
    FIS Requested → FIS Approved
  • 11/28/2022
    Screening → FIS Requested
  • 05/10/2022
    Entered the queue with 259 MW, projected COD 03/31/2028