24INR0275 · BESS · Martin County
Picadillo BESS
Picadillo BESS is a 101 MW battery storage project in Martin County, Texas, connecting at 23837 Buffalo 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 05/15/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0275
- Capacity
- 101 MW
- Fuel
- BESS (BA)
- Substation
- 23837 Buffalo 138kV
- County
- Martin County
- Interconnecting entity
- Black Mountain Energy Storage II
- Projected COD
- 05/15/2028
- Entered queue
- 02/28/2022
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/23/2024FIS Approved → IA Signed
- 06/13/2023FIS Requested → FIS Approved
- 02/28/2022Entered the queue with 101 MW, projected COD 05/15/2028
- 02/28/2022Screening → FIS Requested
Other projects at this substation
No other projects at this substation.