24INR0145 · Gas · Guadalupe County
Calpine Guadalupe Peakers
Calpine Guadalupe Peakers is a 450 MW natural gas project in Guadalupe County, Texas, connecting at 7044 Marion 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/30/2030.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0145
- Capacity
- 450 MW
- Fuel
- Gas (GT)
- Substation
- 7044 Marion 345kV
- County
- Guadalupe County
- Interconnecting entity
- Guadalupe Peaking Energy Center, LLC
- Projected COD
- 05/30/2030
- Entered queue
- 10/18/2021
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/18/2021Entered the queue with 450 MW, projected COD 05/30/2030
- 10/18/2021Screening → FIS Requested
Other projects at this substation
| Guadalupe Battery Storage Project | BESS | 210 MW | FIS Requested |