LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0137 · Solar · Delta County

Eagle Springs Solar

COD delayed 1×

Eagle Springs Solar is a 77 MW solar project in Delta County, Texas, connecting at Tap Lake Creek Substation (#6835) – Enloe Switching station (#6834) 138 kV Line. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 03/29/2027. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0137
Capacity
77 MW
Fuel
Solar (PV)
Interconnecting entity
Eagle Springs Solar, LLC
Projected COD
03/29/2027
Entered queue
10/18/2021
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 02/23/2027 → 03/29/2027 (+1 months)
  • 09/17/2025
    FIS Requested → FIS Approved
  • 04/17/2024
    FIS Approved → IA Signed
  • 06/13/2022
    Screening → FIS Requested
  • 10/18/2021
    Entered the queue with 77 MW, projected COD 02/23/2027

Other projects at this substation

Eagle Springs StorageBESS34 MWIA Signed