Aster Solar is a 160 MW solar project in Guadalupe County, Texas, connecting at 7042 Zorn 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/01/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0115
- Capacity
- 160 MW
- Fuel
- Solar (PV)
- Substation
- 7042 Zorn 345kV
- County
- Guadalupe County
- Interconnecting entity
- Aster Solar
- Projected COD
- 06/01/2029
- Entered queue
- 09/21/2021
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/24/2022Screening → FIS Requested
- 09/21/2021Entered the queue with 160 MW, projected COD 06/01/2029