23INR0637 · Wind · Armstrong County

Goodnight Wind II

Goodnight Wind II is a 261 MW wind project in Armstrong County, Texas, connecting at tap 345kV 23900 Alibates - 23914 Tule Canyon CKT2. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 06/06/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0637
Capacity
261 MW
Fuel
Wind (WT)
Interconnecting entity
FGE Goodnight II, LLC
Projected COD
06/06/2027
Entered queue
08/18/2019
ERCOT zone
PANHANDLE
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/15/2026
    FIS Requested → FIS Approved
  • 05/01/2023
    Screening → FIS Requested
  • 08/18/2019
    Entered the queue with 261 MW, projected COD 06/06/2027
  • 08/18/2019
    FIS Approved → IA Signed