23INR0441 · Wind · Lamar County
Bug Tussle Wind Project
Bug Tussle Wind Project is a 397 MW wind project in Lamar County, Texas, connecting at Tap 1729 Valley South and 1692 Paris. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/18/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0441
- Capacity
- 397 MW
- Fuel
- Wind (WT)
- Substation
- Tap 1729 Valley South and 1692 Paris
- County
- Lamar County
- Interconnecting entity
- Bug Tussle Wind, LLC
- Projected COD
- 09/18/2028
- Entered queue
- 01/13/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/10/2024FIS Requested → IA Signed
- 08/16/2022Screening → FIS Requested
- 01/13/2022Entered the queue with 397 MW, projected COD 09/18/2028
Other projects at this substation
No other projects at this substation.