ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0087 · Solar · Brooks County

Kinenos Solar

Kinenos Solar is a 203 MW solar project in Brooks County, Texas, connecting at tap 345kV 8905 North Edinburg - 8455 Lon Hill. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0087
Capacity
203 MW
Fuel
Solar (PV)
Interconnecting entity
Encino del Sol Energy, LLC
Projected COD
12/31/2029
Entered queue
12/03/2020
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/03/2020
    Entered the queue with 203 MW, projected COD 12/31/2029
  • 12/03/2020
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.