LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0026 · Solar · Lamar County

Baker Branch Solar

Baker Branch Solar is a 469 MW solar project in Lamar County, Texas, connecting at tap 345kV 1692 Paris - 1690 Valley. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 09/30/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0026
Capacity
469 MW
Fuel
Solar (PV)
Interconnecting entity
Mockingbird Solar Center, LLC
Projected COD
09/30/2026
Entered queue
03/05/2020
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/10/2024
    Energization Approved → Sync Approved
  • 04/01/2024
    IA Signed → Energization Approved
  • 10/30/2023
    FIS Requested → FIS Approved
  • 02/14/2022
    FIS Approved → IA Signed
  • 03/05/2020
    Entered the queue with 469 MW, projected COD 09/30/2026
  • 03/05/2020
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.