22INR0203 · Solar · Lamar County

Delilah Solar 2

Delilah Solar 2 is a 318 MW solar project in Lamar County, Texas, connecting at 345 kV TTRSW 11688. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/31/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
22INR0203
Capacity
318 MW
Fuel
Solar (PV)
Interconnecting entity
Delilah Solar Energy II LLC
Projected COD
12/31/2026
Entered queue
11/20/2018
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 01/13/2025
    Energization Approved → Sync Approved
  • 10/29/2024
    IA Signed → Energization Approved
  • 12/22/2020
    FIS Approved → IA Signed
  • 06/09/2020
    FIS Requested → FIS Approved
  • 05/03/2019
    Screening → FIS Requested
  • 11/20/2018
    Entered the queue with 318 MW, projected COD 12/31/2026

Other projects at this substation

Samson Solar 2Solar203 MWSync Approved